Recently, we toured the construction site with project site super,
Brian MacLean who provided us with the latest construction updates on
Aura.
View of Aura from Yonge Street
Currently, Aura's 32nd floor is being poured. The quick progress can be attributed to the use of two systems to pour concrete. The first uses a pumping system that pumps the concrete from the ground level up to the floor that will be poured. As construction progresses upwards, the pump system also moves upwards. The use of cranes lifting buckets to the required floor also helps to speed up the process of pouring concrete for columns. With both systems in place, from start to finish, it takes one week to complete a floor which is pretty impressive considering the enormity of Aura's floor plate size.
Inside the residential tower, the lower and upper floors are at a
different stage of construction. The lower floors are well underway with most of
the drywall, and tiling installed including primer on walls.
Drywall in suites higher up will begin shortly.
Suite With Primer on the Walls
Bed Bath & Beyond Retail Space
Bed Bath & Beyond Offices
All of the retail shops on the subway retail level are now complete
with finishing touches to the the food court happening this week. In the next
couple of months retailers will be moving in to custom outfit their stores and
prepare for their much anticipated public opening later this fall.
Every week something new and exciting is happening at Aura. Check back with us often for more updates.